Penarth Dock, South Wales - 150 years - the heritage and legacy  
Penarth Dock, South Wales - the heritage & legacy . . .

Volume Eight - Pre-Victorian to the present day - more aspects - To dredge the River Ely - 1860's

Since receiving your notice to proceed with my Contract for the River Diversion - I have again tried all that lies in my power to hire a Dredger of sufficient power and length of Bucket Ladder suited to the size of Tides in the River - but up to this time have not been able to succeed - And as Mr Mitchell is now proceeding rapidly with his new and powerful Dredger and which he informs me will be ready for work in two months at furthest - I would therefore humbly beg that you would be so kind as to delay the work until then - when you may rely upon the Contract being complete in a superior manner, and in as short time as if an inferior machine was set at work at once.

The 'humble' response from Mr. Hardie of Newport to the demand to complete his Contract from the Company a few days earlier. The original is held at the National Archives. [142]

© 2014 - 2025 - penarth-dock.org.uk - all rights reserved - web design by Dai the Rat