BARRY RAILWAY VIADUCT - Crossing the Taff Valley - THE HUGE STRUCTURE COMPLETED - The permanent way has been laid across the immense railway viaduct running across the Taff Valley at Taff's Well. It carries the railway and connects the Barry system with the Rhymney system, and in crossing the Taff valley there runs beneath it two roadways, two railway lines — the T.V.R. and the Cardiff Railway — the river Taff, a feeder for the tin works, and the Glamorganshire Canal.
At its highest point it is 112 feet from ground to parapet, while the foundations for one of the pillars run down to a depth of about 30 feet. It is a fine structure with seven large spans varying in size from 120 to 180 feet, and at each end are two brick arches on the mountain slopes. The total length of the structure is 1,420 feet, or nearly double the length of the Porthkerry Viaduct on the Vale of Glamorgan Railway. At its highest point also it is a few feet higher than the latter, while the spans are each nearly four times larger.
The contractors who have executed the work are Messrs Price and Wills, of Westminster, the firm who constructed the No 2 Dock at Barry, Barry Island Railway extension and passenger pontoon. The method adopted was peculiar, although probably the less dangerous for life and limb. The huge icon girders, weighing many tons, were placed on the pillars when these were raised only a couple of feet from the ground, and they were then raised four feet every time the masonry reached the girder, so that when the summit was gained the girders were in position.
The viaduct was designed by Sir John Wolfe Barry, consulting engineer to the Barry Railway Company, for whom Mr. J. Bell, the resident engineer to the company, superintended the progress of the work. It has taken over three years to construct, and is ready for traffic as soon as the cuttings on the Tongwynlais side are finished. There remains, however, little to be done before the line will be ready for opening. - The Cardiff Times [019] [361] 23rd February 1901. |